Installing Inverter vision three
This page outlines the mounting and cable connection process for installing the three-phase SOLARWATT Inverter vision three inverter.
Table of contents
Mount the inverter
Observe all Safety Instructions and requirements for the installer.
Observe the Specifications for the installation location and the maximum and minimum installation distances for the inverter, meter and battery.
Check whether the condition of the wall and the enclosed mounting material are suitable for supporting the product weight of the inverter (22 kg).
- Mark, then drill the screw holes for the wall bracket
- Mount the wall bracket
- Carefully hang the inverter on the wall bracket
- Screw the inverter into both sides of the wall bracket

Video: Inverter vision three wiring
Connect the PV DC cable
Observe the Information on cable requirements and minimum bending radii for inverter, meter and battery.
Observe the Explanations on the Crimping PV plug connectors.
Inverter vision three includes Stäubli MC4 Evo 2A PV connectors in the box, which are compatible with the Stäubli PV connection sockets on the inverter. Stäubli PV plugs are compatible with other types of Stäubli MC4 plugs.
- Strip the PV DC cable to a length of 6.0 - 7.5 mm
Make sure that no individual wires are damaged! - Crimp the DC cable with the PV plug connectors
Ensure correct polarity when assigning the PV pin contacts!
- Connect the DC PV cable to PV+ and PV- on the inverter.
Listen for an audible 'click' to ensure the connector makes contact. - Pull on the DC PV plug connectors to ensure they are fully engaged.
(control force: max. 20 N)
Connect the DC battery cable to the inverter
The Battery DC cable is included in the Battery vision top pack box.
- Connect the plug to BAT+ and BAT-
Listen for an audible 'click' to ensure the connector makes contact.
Screw in the antenna (for Bluetooth support)
The antenna is included in the Inverter vision three box.
- Remove the protective rubber sleeve from the antenna connector on the inverter
- Screw on the antenna
Connect the BMS cable to the inverter
The BMS cable is a standard network cable and is included in the Battery vision top pack box.
- Connect one side of the BMS cable to the BMS port on the inverter.
- Tighten the mechanical strain reliever (this also acts as a waterproofing seal).
Connect the inverter to the internet
Inverter vision three must be connected directly to the router via a LAN cable connection. A LAN cable for this purpose is not included in the scope of delivery.
- Attach the waterproof connection housing and mechanical strain reliever (included in the Inverter vision one box) to the inverter side of the plug for protection
- Connect the other side of the cable to your router
In exceptional cases, the inverter can be connected to a Wi-Fi network in range of the inverter to allow it to connect to the internet.
- Ensure that the antenna is screwed in to the inverter
- Use the SOLARWATT Pro app to configure the Wi-Fi settings on the inverter
Further explanations on Connecting the inverter to the local network via Wi-Fi.
Connect AC / BACKUP
Inverter vision three is designed for operation in the three-phase mains, voltage range 220/230/240 V, frequency 50/60Hz. Other technical requirements must comply with the requirements of the local grid.
Please note the Cable requirements and bending radii for inverter, meter and battery.
The AC / BACKUP plug is included in the Inverter vision three box.

Video: Connecting the AC / BACKUP plug
- Strip the cable end as illustrated below
- Crimp the wire end ferrules onto the cable
- Feed the AC cable through the AC plug components
- Connect the cable ends of the mains connection cable and the backup cable according to the wire designation on the plug
- Fix the locking nut
- Connect the mains cable to the BACKUP/GRID connection
- Close and secure the safety clip
Connect the grounding cable
The grounding cable is not included in the scope of delivery. However, a cable lug for connecting the grounding cable is included in the Inverter vision three box.