Installing Inverter vision one
This page outlines the mounting and cable connection process for installing the single-phase SOLARWATT Inverter vision one inverter.
Table of contents
Mount the inverter
Observe all Safety Instructions and requirements for the installer.
Observe the Specifications for the installation location and the maximum and minimum installation distances between the inverter, meter and battery.
Check whether the condition of the wall and the enclosed mounting material are suitable for supporting the product weight of the inverter (22 kg).
- Mark, then drill the screw holes for the wall bracket
- Mount the wall bracket
- Carefully hang the inverter on the wall bracket along the groove guide
- Screw the inverter into both sides of the wall bracket

Video: Inverter vision one wiring
Connect the PV DC cable
Observe the Information on cable requirements and minimum bending radii for inverter, meter and battery.
Observe the Explanations on the Crimping PV plug connectors.
Inverter vision one includes Stäubli MC4 Evo 2A PV connectors in the box, which are compatible with the Stäubli PV connection sockets on the inverter. Stäubli PV plugs are compatible with other types of Stäubli MC4 plugs.
- Strip the PV DC cable to a length of 6.0 - 7.5 mm
Make sure that no individual wires are damaged! - Crimp the DC cable with the PV plug connectors
Ensure correct polarity when assigning the PV pin contacts!
- Connect the DC PV cable to PV+ and PV- on the inverter.
Listen for an audible 'click' to ensure the connector makes contact. - Pull on the DC PV plug connectors to ensure they are fully engaged.
(control force: max. 20 N)
Connect the DC battery cable to the inverter
The Battery DC cable is included in the Battery vision top pack box.
- Connect the plug to BAT+ and BAT-
Listen for an audible 'click' to ensure the connector makes contact.
Screw in the antenna (for Bluetooth support)
The antenna is included in the Inverter vision one box.
- Remove the protective rubber sleeve from the antenna connector on the inverter
- Screw on the antenna
Connect the BMS cable to the inverter
The BMS cable is a standard network cable and is included in the Battery vision top pack box.
- Connect one side of the BMS cable to the BMS port on the inverter.
- Tighten the mechanical strain reliever (this also acts as a waterproofing seal).
Connect the inverter to the internet
Inverter vision one must be connected directly to the router via a LAN cable connection. A LAN cable for this purpose is not included in the scope of delivery.
- Attach the waterproof connection housing and mechanical strain reliever (included in the Inverter vision one box) to the inverter side of the plug for protection
- Connect the other side of the cable to your router
In exceptional cases, the inverter can be connected to a Wi-Fi network in range of the inverter to allow it to connect to the internet.
- Ensure that the antenna is screwed in to the inverter
- Use the SOLARWATT Pro app to configure the Wi-Fi settings on the inverter
Further explanations on Connecting the inverter to the local network via Wi-Fi.
Connecting the AC-BACKUP
Inverter vision one is designed for operation on the single-phase mains, voltage range 220/230/240 V, frequency 50/60Hz. Other technical requirements must comply with the requirements of the local grid.
Please note the Cable requirements and bending radii for inverter, meter and battery.
The AC-BACKUP plug (red ring) is included in the Inverter vision one box.
- Remove the transport protective covers from the AC-BACKUP port on the inverter
- Strip 40 mm of the AC cable
- Shorten the N conductor and L conductor by 9 mm so that the PE conductor can establish a connection all the way to the end of the cable
- Strip 9 mm of PE, N and L insulation
- Crimp on wire end ferrules
- Feed the AC-BACKUP cable through the AC-BACKUP plug
- Connect the cable cores to PE, N and L as marked on the plug
- Screw the plug together
- Listen for an audible 'click' sound, which indicates the assembly has successfully locked in place
- Connect the AC cable to the AC-BACKUP port on the inverter
- Turn the plug ring to the right until it audibly locks into place
Connect AC-GRID
Inverter vision one is designed for operation in the single-phase mains, voltage range 220/230/240 V, frequency 50/60Hz. Other technical requirements must comply with the requirements of the local grid.
Please note the Cable requirements and bending radii for inverter, meter and battery.
The AC-GRID plug (white ring) is included in the Inverter vision one box.
- Remove the transport protective covers from the AC-GRID connection on the inverter
- Strip 55 mm of the AC cable
- Shorten the N conductor and L conductor by 9 mm so that the PE conductor can always establish a connector right to the end
- Strip 9 mm of PE, N and L insulation
- Crimp on wire end ferrules
- Feed the AC cable through the AC-GRID plug
- Connect the cable cores to PE, N and L as marked on the plug (torque 3.0 ± 0.2 Nm)
- Tightly screw the assembly into place, listening out for an audible 'click' sound
- Connect the AC cable to the AC-GRID port on the inverter
Connect the grounding cable
The grounding cable is not included in the scope of delivery. However, a cable lug for connecting the grounding cable is included in the Inverter vision one box.