Installation Inverter vision one
This page describes the mounting and cable installation for the single-phase SOLARWATT Inverter vision one inverter.
Table of contents
Installing the inverter
Observe all Safety Instructions and requirements for the installer.
Observe the Specifications for the installation location and the maximum and minimum installation distances for the inverter, meter and battery.
Check whether the condition of the wall and the enclosed mounting material are suitable for supporting the product weight of the inverter (22 kg).
- Mark and drill the drill holes using the wall bracket
- Mount the wall bracket
- Carefully hang the inverter on the wall bracket using the groove provided
- Fix the inverter to the wall bracket
Inverter vision one wiring
Connect DC cable PV
Observe the Information on cable requirements and minimum bending radii for inverter, meter and battery.
Observe the Explanations on the Crimping PV plug connectors.
The scope of delivery of the inverter includes Stäubli MC4 Evo 2A PV connectors, which are compatible with the Stäubli PV connection sockets on the inverter. Stäubli PV plugs are compatible with other types of Stäubli MC4 plugs.
- Strip the PV DC cable to a length of 6.0 - 7.5 mm
Make sure that no individual wires are damaged! - Crimp the DC cable with the PV plug connectors
Ensure correct polarity when assigning the PV pin contacts!
- Connect DC cable PV to PV+ and PV-
A 'click' must be audible.
- check for correct engagement by pulling on the plug connectors
(control force max. 20 N)
DC cable Connect battery
The Battery DC cable is included in the scope of delivery of the Battery vision top pack.
- Connect the plug to BAT+ and BAT-
You should hear a 'click'.
Install antenna (for Bluetooth connector)
The antenna is included in the scope of delivery of the Inverter vision one.
- Remove the protective rubber sleeve from the antenna connection
- Screw on the antenna
Connecting the BMS cable
The BMS cable is a standard network cable (included in the scope of delivery of the Battery vision top pack).
- Connect the communication cable to the BMS output
- Tighten the mechanical strain relief (also outdoor seal)
Connect LAN
Inverter vision one is connected directly to the router via a LAN connection. The LAN cable is not included in the scope of delivery.
- attach a waterproof plug housing (included in the scope of delivery) to the inverter side of the plug for protection and mechanical strain relief
- Connect the inverter to the router
In exceptional cases, a WiFi connection can be established for a wireless connector to a WiFi in the vicinity of the inverter.
- Ensure that the antenna is screwed to the inverter
- Use the SOLARWATT Pro app to make the WiFi settings
Further explanations on Integrating the inverter into the local network via WiFi.
Connect AC-BACKUP
Inverter vision one is designed for operation in the single-phase mains, voltage range 220/230/240 V, frequency 50/60Hz.
Other technical requirements must comply with the requirements of the local public grid.
Please note the Cable requirements and bending radii for inverter, meter and battery.
The AC-BACKUP plug (red ring) is included in the scope of delivery of the Inverter one.
- Remove the transport protective covers from the AC-BACKUP connection on the inverter
- Strip 40 mm of the AC cable
- Shorten the N conductor and L conductor by 9 mm so that the PE conductor can always establish a connector right to the end
- Strip 9 mm of PE, N and L insulation
- Crimp on wire end ferrules
- Feed the AC-BACKUP cable through the AC-BACKUP plug
- Connect the cable cores to PE, N and L as marked on the plug
- Screw the plug together
- you will hear a 'click' sound if the assembly is successful
- Connect the AC cable to the AC-BACKUP connection of the inverter
- Turn the plug ring to the right until it audibly clicks into place and is locked
Connect AC-GRID
Inverter vision one is designed for operation in the single-phase mains, voltage range 220/230/240 V, frequency 50/60Hz.
Other technical requirements must comply with the requirements of the local public grid.
Please note the Cable requirements and bending radii for inverter, meter and battery.
The AC-GRID plug (white ring) is included in the scope of delivery of the Inverter one.
- Remove the transport protective covers from the AC-GRID connection on the inverter
- Strip 55 mm of the AC cable
- Shorten the N conductor and L conductor by 9 mm so that the PE conductor can always establish a connector right to the end
- Strip 9 mm of PE, N and L insulation
- Crimp on wire end ferrules
- Feed the AC cable through the AC-GRID plug
- Connect the cable cores to PE, N and L as marked on the plug (torque 3.0 ± 0.2 Nm)
- Allow the plug to 'click' into place and screw tight
- Connect the AC cable to the AC-GRID connection of the inverter
Connecting the grounding
The earthing cable is not included in the scope of delivery. The cable lug for the earthing cable is included in the scope of delivery of the Inverter one.